11KV Transformer & Switchgear

Value

£113,000

Client

GE Oil & Gas

Location

Charleton Road, Montrose

Category
Industrial
About This Project

We installed a 500KVA transformer, HV ring main unit and HV circuit breakers c/w 11KV supply cable and earth fields, extended from the existing incoming supply, to increase the maximum load power capacity of the site. 630mm single cables were installed from the transformer to a new 800A LV panel board with SWA cables installed to various distribution boards and TPN equipment. We worked closely with the supply provider and the client to ensure that the site shut-down was as short as possible and carried out at a time to minimise plant disruption.